slava.energy: UK renewable energy projects

Onley Park, Barby - Solar Photovoltaic PV Generation System

REPD record 10017. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
0.28 MW
Status
Planning Permission Granted
Operator
Ministry of Justice
County
Warwickshire
Region
East Midlands
Country
England
Planning authority
West Northamptonshire
Planning reference
WND/2021/0631
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2022-01-04

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10017. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.