slava.energy: UK renewable energy projects
Greystones Road, Grangetown - Battery Energy Storage System
REPD record 10081. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 60 MW
- Status
- Planning Permission Granted
- Operator
- Sembcorp Utilities UK Limited
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Redcar and Cleveland
- Planning reference
- R/2021/0888/CL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-11-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-10-29: Planning Application Submitted
- 2021-12-17: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10081. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.