slava.energy: UK renewable energy projects
Rhoscrowther - Turbine Wind Farm
REPD record 10084. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12.9 MW
- Status
- Planning Permission Refused
- Operator
- Rhoscrowther Wind Farm Limited
- County
- Pembrokeshire
- Region
- Wales
- Country
- Wales
- Planning authority
- Welsh Government (NSIP)
- Planning reference
- DNS/3261355
- Turbines
- 3
- Turbine size
- 4.3 MW
- Record last updated in REPD
- 2022-02-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-10-11: Planning Application Submitted
- 2022-10-27: Planning Permission Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10084. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.