slava.energy: UK renewable energy projects
East London Sustainable Energy Facility (Thames Gateway Power facility)
REPD record 1013. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 25 MW
- Status
- Abandoned
- Operator
- Biossence & Atco
- County
- London
- Region
- London
- Country
- England
- Planning authority
- Havering
- Planning reference
- P0558.12
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-07-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-08-30: Planning Permission Expired
- 2012-05-10: Planning Application Submitted
- 2012-08-30: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1013. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.