Dog Trap Lane, Minety - Battery Energy Storage Systems
REPD record 10488. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 47.5 MW
- Status
- Revised
- Operator
- Pelagic Energy
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2022/00404
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-01-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-01-17: Planning Application Submitted
- 2022-06-29: Planning Application Withdrawn