slava.energy: UK renewable energy projects
Springhill Solar Park (Northwick)
REPD record 1053. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Greencoat Capital
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Cotswold
- Planning reference
- 11/01247/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-09-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-04-18: Planning Application Submitted
- 2011-07-21: Planning Permission Granted
- 2013-02-01: Operational
- 2018-07-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1053. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.