High Nunton Farm - Solar Farm & Battery Storage
REPD record 10532. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- High Nunton Solar Limited
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Dumfries and Galloway
- Planning reference
- 21/2490/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-06-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-01-07: Planning Application Submitted
- 2025-01-22: Planning Permission Granted
- 2028-01-22: Planning Permission Expired