Balliemeanoch Pumped Hydro Project
REPD record 10603. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Pumped Storage Hydroelectricity
- Capacity
- 1500 MW
- Status
- Planning Application Submitted
- Operator
- Intelligent Land Investments Group
- County
- Argyll and Bute
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00003444
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-10-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-07-04: Planning Application Submitted
Position not held by REPD.