Victory Park Way - Solar Panels
REPD record 10697. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.26 MW
- Status
- Planning Permission Granted
- Operator
- Gardner Aerospace
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Derby
- Planning reference
- 22/00242/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-03-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-02-14: Planning Application Submitted
- 2022-03-31: Planning Permission Granted
- 2025-03-31: Planning Permission Expired