Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 6.5 MW
- Status
- Abandoned
- Operator
- Tesco
- County
- Lothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- West Lothian
- Planning reference
- 0467/FUL/10
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-06-30: Planning Application Submitted
- 2010-12-08: Planning Permission Granted
- 2013-12-08: Planning Permission Expired