Crays Hall Farm - Solar Arrays
REPD record 10778. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 25.6 MW
- Status
- Operational
- Operator
- Boom Power Limited
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Basildon
- Planning reference
- 22/00296/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-06-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-03-01: Planning Application Submitted
- 2023-03-08: Appeal Lodged
- 2023-08-30: Appeal Granted
- 2023-08-30: Planning Permission Granted
- 2023-08-30: Planning Permission Refused
- 2025-08-01: Under Construction
- 2026-05-14: Operational
- 2026-08-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10778. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.