Walpole St Andrew - Battery storage
REPD record 10876. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 100 MW
- Status
- Planning Permission Granted
- Operator
- Alfred Energy Limited
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- King's Lynn and West Norfolk
- Planning reference
- 22/00438/FM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-02-28: Planning Application Submitted
- 2022-09-20: Planning Permission Granted
- 2025-09-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10876. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.