Wormald Green - Battery Energy Storage System
REPD record 10893. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 33 MW
- Status
- Operational
- Operator
- Harmony Energy Limited
- County
- North Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Yorkshire
- Planning reference
- 22/00777/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-03-17: Planning Application Submitted
- 2022-06-14: Planning Permission Granted
- 2022-09-26: Planning Permission Refused
- 2023-08-26: Under Construction
- 2024-09-11: Operational
- 2025-09-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10893. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.