slava.energy: UK renewable energy projects
RUDGE FARM SOLAR FARM
REPD record 1091. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 7 MW
- Status
- Operational
- Operator
- Orta Solar
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- E/2012/0946/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-07-26: Planning Application Submitted
- 2012-12-21: Planning Permission Granted
- 2012-12-22: Under Construction
- 2013-03-28: Operational
- 2016-12-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1091. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.