slava.energy: UK renewable energy projects
Morecombe Offshore Windfarm
REPD record 10922. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Offshore
- Capacity
- 480 MW
- Status
- Planning Permission Granted
- Operator
- Cobra Instalaciones y Servicios S.A & Flotation Energy
- County
- Offshore
- Region
- Offshore
- Country
- England
- Planning authority
- The Planning Inspectorate - National Infrastructure
- Planning reference
- EN010121
- Turbines
- 35
- Turbine size
- 13.7 MW
- Record last updated in REPD
- 2026-03-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-05-31: Planning Application Submitted
- 2025-12-01: Planning Permission Granted
- 2032-12-01: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10922. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.