Upper Newton Farm (Blythe House) - Solar Farm & Battery Storage
REPD record 10978. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 30 MW
- Status
- Planning Permission Granted
- Operator
- Innova Renewables
- County
- Staffordshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Staffordshire Moorlands
- Planning reference
- SMD/2022/0160
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-03-24: Planning Application Submitted
- 2023-02-01: Planning Permission Granted
- 2028-02-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 10978. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.