Eastman Peboc Factory
REPD record 11. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 31 MW
- Status
- Appeal Refused
- Operator
- Eastman Peboc Factory
- County
- Gwynedd
- Region
- Wales
- Country
- Wales
- Planning authority
- Isle of Anglesey
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-12-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-01-15: Planning Application Submitted
- 2012-05-15: Planning Permission Refused
- 2013-07-15: Appeal Lodged
- 2013-07-31: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.