Port Clarence Biomass Plant
REPD record 110. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 40 MW
- Status
- Under Construction
- Operator
- Glennmont Partners
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Stockton-on-Tees
- Planning reference
- S/CON/0038/10/P
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-07-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-01-14: Planning Application Submitted
- 2010-02-23: Planning Permission Granted
- 2013-02-23: Planning Permission Expired
- 2015-11-17: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 110. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.