slava.energy: UK renewable energy projects
Tudworth Field Road, Hatfield - Solar Panels
REPD record 11086. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.18 MW
- Status
- Under Construction
- Operator
- SJS Agriplant Limited
- County
- South Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Doncaster
- Planning reference
- 22/00698/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-04-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-03-30: Planning Application Submitted
- 2022-04-01: Under Construction
- 2022-07-06: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11086. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.