slava.energy: UK renewable energy projects
Stoneclough - Battery Energy Storage
REPD record 11161. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 7 MW
- Status
- Planning Permission Granted
- Operator
- GAM Capital Limited & Infinis Energy Services Limited
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Bolton
- Planning reference
- 13256/22
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-05-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-04-11: Planning Application Submitted
- 2022-10-24: Planning Permission Granted
- 2025-10-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11161. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.