slava.energy: UK renewable energy projects
Kincraig - Solar Farm and battery storage system
REPD record 11177. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 21 MW
- Status
- Under Construction
- Operator
- Renewable Connections Developments Limited
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2022/0838
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-06-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-04-14: Planning Application Submitted
- 2022-10-18: Planning Permission Granted
- 2024-10-01: Under Construction
- 2025-10-18: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11177. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.