Pegham Renewable Energy Facility
REPD record 112. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 2 MW
- Status
- Planning Permission Expired
- Operator
- L&S Waste Management
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 11/00136/HCS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-07-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-01-24: Planning Application Submitted
- 2011-04-07: Planning Permission Granted
- 2014-04-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 112. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.