slava.energy: UK renewable energy projects
RITHERDENS FARM solar park
REPD record 1121. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 9.5 MW
- Status
- Planning Permission Refused
- Operator
- a private individual (name not shown)
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 07/13/0016
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-09-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-05-09: Planning Application Submitted
- 2013-08-22: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1121. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.