Harrington Franklin, Richborough Energy Park - Battery Storage
REPD record 11449. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Under Construction
- Operator
- EDP Renewables
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Dover
- Planning reference
- 22/00705
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-06-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-06-01: Planning Application Submitted
- 2022-12-06: Planning Permission Granted
- 2024-12-01: Under Construction
- 2025-12-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11449. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.