slava.energy: UK renewable energy projects
Ford Research And Engineering Centre, Dunton - Solar Farm
REPD record 11486. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.2 MW
- Status
- Operational
- Operator
- Ford Motor Company Limited
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Basildon
- Planning reference
- 22/00748/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-03-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-06-10: Planning Application Submitted
- 2023-02-28: Planning Permission Granted
- 2024-11-01: Under Construction
- 2025-01-31: Operational
- 2026-02-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11486. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.