slava.energy: UK renewable energy projects
Newlands Meadow, Eden - Solar Panels
REPD record 11518. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.15 MW
- Status
- Planning Permission Granted
- Operator
- Hollywood Bowl Group
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 22/06368/PNP14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-06-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-06-10: Planning Application Submitted
- 2022-08-04: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11518. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.