slava.energy: UK renewable energy projects
Studley Farm - Solar Farm & Battery Storage
REPD record 11620. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Under Construction
- Operator
- Aura Power
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2021/08690
- Turbines
- not held by REPD
- Turbine size
- 19.6 MW
- Record last updated in REPD
- 2026-10-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-09-30: Planning Application Submitted
- 2022-06-09: Planning Permission Granted
- 2025-06-09: Planning Permission Expired
- 2026-09-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11620. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.