slava.energy: UK renewable energy projects
Colbrans Farm Estate, Laughton - Battery Storage
REPD record 11682. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 30 MW
- Status
- Planning Permission Granted
- Operator
- Innova
- County
- East Sussex
- Region
- South East
- Country
- England
- Planning authority
- Wealden
- Planning reference
- WD/2024/2392/MEA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2024-12-18: Planning Application Submitted
- 2025-07-21: Planning Permission Granted
- 2028-07-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11682. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.