slava.energy: UK renewable energy projects
Little Park Farm
REPD record 1172. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 8.6 MW
- Status
- Planning Application Withdrawn
- Operator
- Solar Power Generation Ltd
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 12/04673/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-02-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-12-05: Planning Application Submitted
- 2013-02-08: Planning Application Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1172. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.