slava.energy: UK renewable energy projects
Wadley Hill Farm
REPD record 1174. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Refused
- Operator
- Lightsource Renewable Energy
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- South Oxfordshire
- Planning reference
- P15/S2202/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-11-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-01: Planning Application Submitted
- 2015-10-30: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1174. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.