slava.energy: UK renewable energy projects
Concorde Way, Segensworth - Solar Panels
REPD record 11755. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.04 MW
- Status
- Under Construction
- Operator
- Solar Advanced Systems T/A SAS Energy
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 22/01583/PNSOL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-07-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-07-19: Planning Application Submitted
- 2022-11-30: Planning Permission Granted
- 2023-03-16: Under Construction
- 2024-11-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11755. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.