slava.energy: UK renewable energy projects
Hatchlands Farm
REPD record 1176. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.2 MW
- Status
- Operational
- Operator
- Orta Solar
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- South Hams
- Planning reference
- 23/1754/12/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-03-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-10-23: Planning Permission Expired
- 2012-08-01: Planning Application Submitted
- 2012-10-23: Planning Permission Granted
- 2012-12-03: Under Construction
- 2013-03-25: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1176. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.