slava.energy: UK renewable energy projects
Pepperhill Solar Farm - Solar Farm & Battery Storage
REPD record 11800. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Operational
- Operator
- Low Carbon
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 22/03068/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-06-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-07-22: Planning Application Submitted
- 2023-06-07: Planning Permission Granted
- 2026-06-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11800. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.