slava.energy: UK renewable energy projects
Cefn-Y-Maes Farm, Rhydycroesau - Solar Park
REPD record 11859. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.23 MW
- Status
- Planning Permission Granted
- Operator
- Positech Energy Limited
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 22/03447/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-10-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-07-26: Planning Application Submitted
- 2022-10-14: Planning Permission Granted
- 2025-10-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11859. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.