Parkend Crossgates - Solar Panels & Battery Storage
REPD record 11861. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 30 MW
- Status
- Planning Permission Granted
- Operator
- Greentech Projects Holding UK Limited
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 22/03982/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-04-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-11-28: Planning Application Submitted
- 2024-03-07: Planning Permission Granted
- 2027-03-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11861. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.