slava.energy: UK renewable energy projects
Union Hall Road, Lemington - Battery Energy Storage Facility
REPD record 11882. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- Newton Energi
- County
- Tyne And Wear
- Region
- North East
- Country
- England
- Planning authority
- Newcastle upon Tyne
- Planning reference
- 2022/0869/01/DET
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-08-04: Planning Application Submitted
- 2023-01-20: Planning Permission Granted
- 2026-01-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11882. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.