Biffa Electricity Generating Compound, Burtonhead Road - Battery Storage
REPD record 11906. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 1 MW
- Status
- Planning Permission Granted
- Operator
- Biffa Waste Services Limited
- County
- Merseyside
- Region
- North West
- Country
- England
- Planning authority
- St. Helens
- Planning reference
- P/2022/0557/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-11-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-08-04: Planning Application Submitted
- 2022-10-18: Planning Permission Granted
- 2025-11-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11906. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.