Barrow in Furness - Barrow Green Hydrogen Hub
REPD record 11914. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Hydrogen
- Capacity
- 35 MW
- Status
- Under Construction
- Operator
- Carlton Power
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Westmorland and Furness
- Planning reference
- B09/2022/0869
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-10-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-12-16: Planning Application Submitted
- 2023-06-16: Planning Permission Granted
- 2026-07-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11914. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.