Wynyard Business Park, North Chapell Lane - Solar Panels
REPD record 11993. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.96 MW
- Status
- Planning Permission Granted
- Operator
- Northumberland Estates Limited
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Stockton-on-Tees
- Planning reference
- 22/1800/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-10-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-08-12: Planning Application Submitted
- 2022-10-06: Planning Permission Granted
- 2025-10-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 11993. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.