slava.energy: UK renewable energy projects
Garleys Wood Solar Park
REPD record 1218. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Refused
- Operator
- Wessex Solar Energy
- County
- Avon
- Region
- South West
- Country
- England
- Planning authority
- North Somerset
- Planning reference
- 12/P/1654/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-09-19: Planning Application Submitted
- 2012-12-10: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1218. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.