Redcote Lane, Armley - Battery Storage Facility
REPD record 12224. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 60 MW
- Status
- Planning Permission Granted
- Operator
- Cambridge Power Limited
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Leeds
- Planning reference
- 22/05849/FU
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-05-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-09-15: Planning Application Submitted
- 2023-05-18: Planning Permission Granted
- 2026-05-18: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12224. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.