slava.energy: UK renewable energy projects
Heathland House, High Dike - Biomass Boiler
REPD record 12261. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 0.25 MW
- Status
- Planning Permission Granted
- Operator
- R G Simpson Limited
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Kesteven
- Planning reference
- s22/1826
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-09-15: Planning Application Submitted
- 2023-01-25: Planning Permission Granted
- 2026-01-25: Planning Permission Expired