Berrington Farm - Solar Array
REPD record 12266. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 30 MW
- Status
- Planning Permission Granted
- Operator
- Econergy International Limited
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 22/04355/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-09-27: Planning Application Submitted
- 2024-03-26: Planning Permission Refused
- 2025-05-02: Planning Permission Granted
- 2028-05-02: Planning Permission Expired
Open this area on the map