slava.energy: UK renewable energy projects
BH Energy Gap - Waste Energy Plant, The 3Rs
REPD record 12292. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 49 MW
- Status
- Under Construction
- Operator
- BH EnergyGap
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Walsall
- Planning reference
- 19/1172
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-05-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-09-09: Planning Application Submitted
- 2020-11-26: Planning Permission Granted
- 2023-11-26: Planning Permission Expired
- 2025-01-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12292. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.