slava.energy: UK renewable energy projects
Charrington Bowl, Kingston Road - Solar Panels
REPD record 12317. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.28 MW
- Status
- Planning Permission Refused
- Operator
- Mayfair Capital Property Unit Trust
- County
- Surrey
- Region
- London
- Country
- England
- Planning authority
- Kingston upon Thames
- Planning reference
- 22/02516/PRA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-11-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-09-27: Planning Application Submitted
- 2022-10-25: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12317. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.