The Bungalow, Kus Industrial Estate - Solar Photovoltaic Panels
REPD record 12362. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.05 MW
- Status
- Planning Permission Granted
- Operator
- Boardlink Limited
- County
- Clwyd
- Region
- Wales
- Country
- Wales
- Planning authority
- Flintshire
- Planning reference
- FUL/000530/22
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-12-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-10-03: Planning Application Submitted
- 2022-12-02: Planning Permission Granted
- 2027-12-02: Planning Permission Expired