Greenock Headworks, Eldon Street - Solar Panels
REPD record 12420. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.23 MW
- Status
- Planning Permission Granted
- Operator
- Scottish Water Horizons
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Inverclyde
- Planning reference
- 22/0231/IC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-01-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-10-07: Planning Application Submitted
- 2022-12-02: Planning Permission Granted
- 2025-12-02: Planning Permission Expired