slava.energy: UK renewable energy projects
Oaklands Farm
REPD record 1258. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 11.4 MW
- Status
- Revised
- Operator
- Pegasus Group
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Ashford
- Planning reference
- 13/01022/AS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-02-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-09-12: Planning Application Submitted
- 2013-12-23: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 1258. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.