Westbury Sewage Treatment Works, Slag Lane - Solar Panels
REPD record 12610. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- not held by REPD
- Status
- Planning Permission Granted
- Operator
- Wessex Water
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- PL/2022/06569
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-11-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-08-23: Planning Application Submitted
- 2022-10-24: Planning Permission Granted