slava.energy: UK renewable energy projects
Trinity Hall Solar Farm
REPD record 12623. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 15 MW
- Status
- Under Construction
- Operator
- European Energy Photovoltaics Limited
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Central Bedfordshire
- Planning reference
- CB/21/00437/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-01-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-02-11: Planning Application Submitted
- 2021-05-05: Planning Permission Granted
- 2021-08-09: Planning Permission Refused
- 2023-08-09: Planning Permission Expired
- 2025-02-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 12623. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.